Deerfield Beach Permit Information

To access the Deerfield Beach website regarding building permits, please click here.
To compare all Broward County municipalities' permit requirements, click here

 

Permit Submittal Requirements for the Deerfield Beach:

BROWARD COUNTY ENVIRONMENTAL PROTECTION DIVISION
EPD submittal / Approval required prior to Bldg Dept submittal. Apply 'on-line' for Security Code & Application Number. Walk-thru review. Impact Fees will be determined, if any. Submit Asbestos form if Interior only or if renovation/addition.

ELEVATOR

Broward County Elevator submittal / Approval required prior to Bldg Dept submittal. Submit plans only for review, Application not required. Allow 1 week review time.

NOTICE OF COMMENCEMENT

Recorded NOC required prior to Bldg Dept submittal. Record NOC at County Recording office. Secure 2 Certified copies.  If value of Work is under $2,500, NOC Not required.

PERMIT APPLICATION

Must be in Black ink. Values, SF & Quantities required. Must be signed by Owner & Contractor. Copy of Contractor's Lic & Insur is required.

SURVEYS
Current s/s copies required. None required if interiors only. 

ENERGY CALCULATIONS
Must be s/s by engineer. None required if interiors only. Required for change in occupancy in space cooling or added energy usage.

SPECIAL INSPECTION FORMS
May be required for interiors also depending upon type and extent of work

STRUCTURAL CALCULATIONS
May be required for interiors also depending upon type and extent of work

ORIGINAL DEVELOPMENT REVIEW COMMITTEE PLANS
Must submit stamped / original signed Approved plans. None required if Interiors only.

OWNER/AGENT LETTER
Letter must have Owner and Agent notarized signatures.

NUMBER OF SETS
Two sets.

TRADE APPLICATIONS
Must be in Black ink. Values, SF & Quantities required. Must be signed by Owner & trade Contractor. Copy of Lic & Insurance is required.

NOTICE OF ACCEPTANCE

Product Approval Review Form required.

ROOF CALCULATIONS (HVC)
Must be complete package with roof NOA's and roof plan. None required if Interiors only.

ROOF TRUSS SHOP DRAWINGS
Must be s/s by engineer and include all calcs. None required if Interiors only.

FIRE SPRINKLER ALARM DRAWINGS
Must have hydraulic calcs and cut sheets of all devices and panels.

COMMENTS

REVISIONS: Need Revision Submittal form.  Need Architect's Narrative. Need clouds and deltas. Signatures are required.

FLOOD CERTIFICATIONS
Required for new construction, substantial improvements and additions.