Permit Submittal Requirements for Weston:

BROWARD COUNTY ENVIRONMENTAL PROTECTION DIVISION
EPD submittal / Approval required prior to Bldg Dept submittal. Apply 'on-line' for Security Code & Application Number. Walk-thru review. Impact Fees will be determined, if any. Submit Asbestos form if Interior only or if renovation / addition.

ELEVATOR

Broward County Elevator submittal / Approval required prior to Bldg Dept submittal. Submit plans only for review, Application not required. Allow 1 week review time.

NOTICE OF COMMENCEMENT

Recorded NOC required prior to Bldg Dept submittal. Record NOC at County Recording office. Secure 2 Certified copies.  If value of Work is under $2,500, NOC Not required.

PERMIT APPLICATION

License & insurance for every submittal. Except Revisions.  

SURVEYS
Current s/s copies required. None required if interiors only.

ENERGY CALCULATIONS
Must be s/s by engineer.  None required if interiors only. 

SPECIAL INSPECTION FORMS
Must be s/s by engineer and must be signed by Owner. None required if interiors only.

STRUCTURAL CALCULATIONS

Must be s/s by engineer. Not required by interiors only.

ORIGINAL DEVELOPMENT REVIEW COMMITTEE PLANS

Must submit stamped / original signed Approved plans. None required if Interiors only.

OWNER/AGENT LETTER
GC Qualifier can sign for Owner.

NUMBER OF SETS
Two sets.

TRADE APPLICATIONS
License & insurance for every submittal. Separate check req'd for ea trade.

NOTICE OF ACCEPTANCE

Must be stamped by architect. Windows, Doors, Louvers, Shutters, etc.

ROOF CALCULATIONS (HVC)
Must be complete package with roof NOA's and roof plan. None required if Interiors only.

ROOF TRUSS SHOP DRAWINGS
Must be s/s by engineer and include all calcs. None required if Interiors only.

FIRE SPRINKLER ALARM DRAWINGS
Must have hydraulic calcs and cut sheets of all devices and panels.

COMMENTS

REVISIONS: Permit Application is required. Owner not required to sign Application. Need Architect's Narrative. Need clouds and deltas. Do Not return Void sheets. Separate check required ea trade.